Maintenance was completed, and most of the cluster came up last night, including the ability to log into the login node, access files, and submit jobs. We will be addressing any cluster nodes that are still down later today.
Posted Oct 30, 2025 - 07:45 CDT
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Oct 29, 2025 - 15:12 CDT
Scheduled
Maintenance of the datacenter requires that the HPC system is powered off. We may take the opportunity to install some system updates after it is powered back on.
No jobs will run or be accepted during this time. Queued jobs should continue once the maintenance downtime has completed. Jobs submitted with a runtime that intersects with the maintenance window will not start, with the reason "ReqNodeNotAvail, Reserved for maintenance".
Posted Oct 29, 2025 - 15:12 CDT
This scheduled maintenance affected: High Performance Computing (HPC) System (Login Nodes, Cluster Nodes and Jobs, Home and Scratch File Systems).